INDUSTRIAL WASTEWATER AND ZLD / 03
Carbon bed for very strong, toxic wastewater.
For wastewater so strong it kills ETP bacteria.
Wastewater from pesticide, dye or chemical plants is so strong it kills the bacteria in the ETP. Hydrogen peroxide is added and passes over carbon coated with iron.
What it achieves
The key numbers.
per 1,000 litres to run.
sludge.
from treatment.
Problem and fix
The problem this solves.
- 01The problem
Wastewater from pesticide, dye or chemical plants is so strong it kills the bacteria in the ETP.
How it is fixedHydrogen peroxide is added and passes over carbon coated with iron. Together they make a strong cleaning agent that breaks down the pollution. The iron stays on the carbon, so no iron sludge forms.
How it works
Step by step.
- 1
Dose
A little hydrogen peroxide is added.
- 2
React
It flows over carbon coated with iron.
- 3
Destroy
Strong cleaning agents form and break down the pollution.
- 4
Discharge
The iron stays on the carbon, so no iron sludge forms.
Key features
Why it works well.
INR 12 to 15 per 1,000 litres.
- Handles toxic wastewaterPesticide, dye and chemical effluent.
- No iron sludgeUnlike normal Fenton treatment.
- Small footprintA packed bed, not a big tank.
- Low powerLittle electricity needed.
At a glance
The details.
| Treats | Very high COD, toxic organics |
|---|---|
| Running cost | INR 12 to 15 per 1,000 litres |
| Sludge | Very little |
| Ready level | Level 9 of 9 (already in use) |
| Scale | Full-size plants |
| Used in | Pesticide, dye, chemical |
Costs are indicative and change with your water, site and plant size. We confirm them after testing a sample.
Where it is used
Who it is for.
- Pesticide makers
- Dye intermediate units
- Chemical plants
Questions
Frequently asked questions.
Is this technology proven?
Yes. It is at ready level 9 of 9, which means: already in use. INR 12 to 15 per 1,000 litres.
What does it cost to run?
About iNR 12 to 15 per 1,000 litres. The exact figure depends on your water and the size of the plant. We confirm it after testing a sample.
Can we try it on our own water first?
Yes. We test a sample in our NABL-accredited lab and, where it helps, run a small trial on your site before you invest in a full plant.
Do you supply and install it?
Yes. We design, supply, install and start up the system, train your staff, and our lab checks the treated water.
Factory wastewater that fails COD, smells or makes too much sludge
Other ways to fix this problem.
THE NEXT STEP
Fix it on
your own site.
Send us a water sample or a test report. We will check it, confirm this method fits and tell you what it costs to run.
Discuss your problem